Pre-Shipment Inspection: What to Check Before a Machine Leaves

The expensive failures in this trade do not happen in the factory. They happen in the four weeks between crating and commissioning, when a missing part, a wrong voltage or a braced door nobody documented turns into a stopped installation on the other side of the world.

This is the list we would use if we were the buyer. It assumes the commercial questions — price, warranty, terms — are already settled, and it is only about the machine in front of you.

Eight checks, in the order they matter

01
Run with abrasive, not empty
An empty run proves the motor turns. A loaded run proves the wheels throw, the elevator lifts and the separator classifies — the three things that actually fail on arrival.
02
Blast your own sample
Send parts ahead and have them blasted in the factory. The finish you accept at home is the finish they have to reproduce; agreeing on a photograph is not the same thing.
03
Voltage test at your voltage
The panel must be wired for your supply and energised at it before crating. A machine tested at 380 V and shipped to a 480 V site has not been tested.
04
Sound and leak check under load
Run it and listen: a rhythmic knock is a wheel or bearing, a whistle is a leaking seal. Walk the chamber with a lamp while it runs and look for dust escaping at the door.
05
Panel and label audit
Every pushbutton, gauge and safety interlock labelled in a language your operators read, with the wiring diagram matching what is in the cabinet.
06
Wear parts and spare set counted
Photograph the crate contents against the packing list. This is the moment a missing cage is discovered, not eight weeks later.
07
Loose parts removed for transit
Hangers, doors and anything that swings must be braced or removed. Ask what was taken off — it has to be refitted at site.
08
Documents travel with the machine
Test report, wiring diagram, manual, and the name and contact of the engineer who will answer commissioning questions.

If you cannot travel

Most buyers do not fly out for a machine. That is fine, but it changes what the evidence has to be. Three things substitute for being there, in descending order of usefulness:

  • Your parts, blasted by them — the strongest evidence, because it tests the machine against your actual job rather than against a demonstration piece.
  • An unedited video of the loaded run — a single continuous take, with the machine serial number visible at the start and the finish at the end. Edited clips prove nothing.
  • A third-party inspector — worth it on a large line, and worth specifying who pays for the re-inspection if the item fails.

The documents that prevent arguments later

A machine arrives with a crate and a folder. The folder is what you will be reading at 2 a.m. during commissioning, so check it before the crate is closed:

On the voltage point there is a longer note worth reading before you approve the panel: how a machine is configured for a specific grid.

  • Test report with the actual readings, not a blank template
  • Wiring diagram matching the panel as built
  • Manual with maintenance intervals and torque values
  • Packing list that matches the photographs you took
  • The contact of the engineer who will answer questions, not a general sales address

What "acceptance" should mean

Acceptance is not the moment the machine is paid for. It should be the moment a defined sample reaches a defined grade at a defined rate — and it is worth writing that sentence into the order rather than assuming it.

If the sample is blasted at the factory, keep it. A physical reference part settles more arguments than any certificate, because both sides can put it next to the disputed batch and look.

Questions buyers ask

Can I inspect before the balance payment?
That is the normal arrangement: inspection and the loaded run before the balance, shipment after it. Put it in the order, not in an email.
What if I find a problem at inspection?
It is corrected in the factory, which is the cheapest place to correct it. That is the entire argument for inspecting before crating rather than after arrival.
Do you provide the test report?
Yes, with the machine, along with the wiring diagram and manual. Ask for the readings rather than a signature.

Related: how a machine is checked before it leaves, delivery, warranty and payment questions, the seven checks before you choose a supplier.

Want to witness the run?

Send your sample parts ahead and come for the loaded test — or ask for the unedited video with the serial number in frame.

Arrange an inspection