Questions buyers ask before ordering
Everything we get asked between the first email and the purchase order — selection, delivery, warranty, spare parts, and what happens after the machine lands. If your question is not here, it is probably the one we should add.
Choosing the machine
Which type of shot blasting machine do I need?
It follows the part, not the budget. Parts that can fall against each other go in a tumble belt; large or fragile parts that must not be tumbled go on a hook; thin small parts that need continuous feed go on a mesh belt; long plates and profiles go on a roller conveyor. Send a drawing or a photo next to a ruler and we will tell you which of the four fits.
Why is there no price list on the website?
Because the price is the configuration. Chamber width sets the number of blast wheels — four from 600 to 1,000 mm, six from 1,000 to 1,500 mm, eight from 1,500 to 2,500 mm — and wheel power, liner specification, dust collector, loading method and voltage all move with it. A number published without those inputs would be either misleading or meaningless.
Can you build a machine wider than the standard sizes?
Yes, up to 3,000 mm of working width. Between 2,500 and 3,000 mm each machine is drawn individually, because above eight wheels the layout stops being a catalogue item. The final decision is made on the opening width together with the opening height, since the height decides where the wheels sit.
Reading two quotations side by side
How do I compare two quotations for the same part?
Put six lines side by side: number of blast wheels and the power of each; chamber dimensions against your largest part, including its rotation envelope; dust collector air volume and whether it is included; whether every wheel has a VFD; the wear-part material and the first spare set; and what is excluded (foundation, installation, commissioning, freight). A quotation that is cheaper on the machine and dearer on those six lines is not cheaper.
A supplier quotes more wheels than another. Is that better?
Only if the chamber is wider. Wheel count follows working width because adjacent wheels must overlap — four wheels from 600 to 1,000 mm, six to 1,500, eight to 2,500. Two machines of the same width with different wheel counts means one of them is either over-blasting the middle of the part or failing to reach its edges. Ask for the chamber dimensions, then check the wheel count against them.
What is usually left out of a quotation that I should ask about?
Foundation and pit work, unloading at your site, installation and commissioning, the first fill of abrasive, operator training, and whether the dust collector and ducting are inside or outside the price. None of these are optional in practice, so a quotation without them is incomplete rather than competitive.
Should I accept a machine built to my part or a standard size?
A standard chamber slightly larger than your part is usually the best value — you get proven drawings and a shorter lead time. Custom is worth paying for when the part will not fit at all, when the envelope is unusually tall or narrow, or when the volume justifies a dedicated layout. A custom build that is only marginally bigger than standard buys you nothing but a longer schedule.
Order, delivery and payment
How long is delivery?
The Q326 and Q3210 tumble belt machines are held in stock and ship in 7 to 10 days from order. A custom tumble belt build takes about 15 days. For other models the date is confirmed in the quotation rather than promised from a shelf.
What warranty do you offer?
One to two years depending on the application, written into the quotation. Wear parts are excluded, as they are on any blast machine — which is why we keep them in stock.
What are the payment terms?
30% T/T with the order and 70% before shipment. Other arrangements are possible for repeat customers and for projects with a long manufacturing cycle.
Spare parts and after-sales
How fast can I get spare parts?
Blast wheels, blades and liners ship by air freight and reach most countries in about 7 days. For a machine running two shifts, one spare set of blades on the shelf is the difference between a maintenance morning and a week of lost production.
Do you supply the dust collector with the machine?
Yes. Dust extraction is sized with the machine — the air volume in the specification table is the figure the collector has to handle — and it ships as part of the unit rather than as a separate purchase.
Accepting the machine on arrival
What should we check before the machine is unloaded?
Before the carrier’s document is signed: count the crates against the packing list, read the nameplate on each unit against the order, and photograph any damage to crating, panels or paint. Then read the motor nameplate voltage and frequency against the supply on site. Damage found after the truck has left is the carrier’s word against yours, and a voltage mismatch discovered at first start has already cost you a week.
What has to be right before the first start?
Four things. The foundation or pit against the drawing — on a roller conveyor the depth below ground is fixed per model, from 1,616 mm on the Q6912 to 3,170 mm on the Q6940, and it is the figure most often discovered too late. The abrasive charge filled and the separator gate set for the shot size you are running. The blast wheel rotation direction checked against the arrow on the housing before any abrasive is fed. And every blade, liner plate and cage bolt tightened to torque — a liner that lets go in the first hour takes the wheel housing with it.
How is the surface result proven before we sign off?
Run your own parts, at the speed and shot flow you will actually production-run, and record what comes out: the SA grade against the ISO 8501-1 comparators, the profile depth if your coating specification names one, and the cycle time per batch or per metre. A machine accepted on a demonstration part from the supplier, but never run on your part, has not been accepted — it has only been delivered.
Warranty and wear parts in practice
Why is the warranty quoted as one to two years rather than a fixed number?
Because it is set against the duty the machine is bought for, and it is written into the quotation before the order rather than negotiated after a failure. The application you describe at the quotation stage — material, hours per shift, abrasive, surface standard — is what the period is agreed on.
Which parts sit outside the warranty, and why?
The wear parts: blast blades, impellers, control cages, directional sleeves, chamber liners and disc seals. Their life is set by shot flow and running hours rather than by the calendar, so they are consumables on every blast machine made by anyone. That is also why they are held in stock and air-freighted in about seven days instead of being treated as a claim when they wear out.
What should we keep on the shelf from day one?
For a machine running two shifts: one spare set of blades, one control cage with its directional sleeve, and a disc seal. It is the difference between a maintenance morning and a week of lost production, the parts are small enough to air-freight cheaply, and in most markets they cannot be bought locally at the right grade.
What comes with the machine
Is the dust collector part of the machine or a separate purchase?
Part of it. The air volume printed in the specification table is the figure the collector is sized to, and it ships with the unit rather than as an option added later — so extraction capacity matches the blast wheels instead of trailing them by a size.
What arrives with a unit?
The machine, its dust collector and ducting, the control cabinet wired and run-tested at the voltage and frequency you specified, and the installation drawings the machine was built to — so the pit, the foundation bolts and the duct route can be prepared while it is still in transit rather than after it lands.
Working with us
How quickly will I get a reply?
One working day. Inquiries reach us by email and are answered in the order they arrive. If your message arrives late on a Friday in Europe or the Americas, the answer comes on Monday. If a drawing or photo is attached, the first reply usually includes a suggested model rather than a request for more information.
What should I send with the first message?
Five things let us size a machine without a second round of emails: the workpiece material, the largest and heaviest piece, the surface standard you must reach (SA 2.5, SA 3.0, or a Ra value), the throughput you need per shift, and your plant voltage and frequency. A photo of a part next to a ruler is often more useful than a description.
Can the machine be built for our plant voltage?
Yes. Machines are built for 380V, 415V, 440V, 460V, 480V, 600V or 220–230V at 50 or 60 Hz, and each unit is wired and run at that voltage in our factory before it is crated. Nothing has to be rewired or re-tapped on site, and no external transformer is needed.
Do you send engineers for installation?
For projects that need it, yes. Two engineers spent seven days in Surabaya on the Q3740 project — installation, commissioning, operator training and the first production runs — and a machine delivered to Uzbekistan was running within seven days of arrival. Simple installations are handled remotely: a Bangladeshi foundry installed a Q378 and a Q3210 themselves from our drawings.
What certification do the machines carry?
The company holds ISO 9001:2015, certified in January 2025, and CE certification to 2006/42/EC, granted in August 2025. Electrical components inside the cabinet are sourced from Schneider and Siemens for machines shipped to markets that require it.
Can we visit the factory before ordering?
Yes. The factory is in Botou, Cangzhou, Hebei — about two hours by high-speed train from Beijing. Visits are arranged in advance so the model you are considering can be run with your own workpieces while you are there.
Still unanswered
Send the part drawing, the batch weight and your plant voltage. That is usually enough for a model recommendation in the first reply, without a second round of questions.
Ask a Specific QuestionRelated: which machine type fits your part · how configuration sets the price · the range overview PDF · tumble belt range, hook type range, roller conveyor range and spare parts.